Project Background

One of the busiest acute NHS hospitals in the South East of England serves a catchment area of around 500,000 people across Brighton and the wider region. As a major trauma centre operating around the clock, uninterrupted climate control is not optional, it is critical to patient safety, operating theatres, and the preservation of temperature-sensitive pharmaceuticals and equipment.

Rapid Energy were called in after the hospital’s cooling system deteriorated to the point where only one of four installed chillers remained operational. With the remaining units failing and summer demand approaching, the risk to the site was significant, so our engineers were mobilised immediately.

360kW Heat Pump Chiller

Equipment

All hired equipment was specified to meet the hospital’s full cooling demand and provide complete redundancy in the event of any unit fault, including:

  • 4 x 360kW Heat Pump Chillers
  • Integral Pumps
  • Flow & Return Header Assembly
  • Railway Sleeper Base Packs

Challenges

  • Height restrictions for the crane – The rooftop location required careful planning around overhead height limitations at the site, restricting crane reach and positioning options. 
  • Tight footprint for four large units – Fitting four 360 kW packaged chillers onto the roof whilst maintaining the manufacturer’s required ventilation clearances between each unit was a significant spatial challenge. 
  • Maintaining ambulance access throughout – The hospital’s emergency vehicle routes could not be obstructed at any point. All crane positioning, delivery vehicle movements, and equipment staging had to work entirely around live ambulance access.
  • Complete delivery and unloading in a single day – To minimise disruption to the hospital, all four chillers had to be craned into position and the site cleared within one working day. 

 

            Royal Sussex County Hospital - Chiller      Royal Sussex County Hospital - Chiller      Royal Sussex County Hospital - Chiller

 

Our Solution

  • Rapid Energy carried out a detailed site survey and worked with a specialist lifting contractor to plan a safe and efficient rooftop installation.
  • All four 360kW chillers were lifted and positioned within a compact 8m x 8m footprint, while maintaining required ventilation gaps between each unit.
  • Railway sleepers were installed to evenly distribute the load across the rooftop and raise the equipment approximately 200mm above drainage covers.
  • Each chiller was carefully positioned to ensure safe access to control panels and key components for future maintenance.
  • The system was fully integrated with pumps and a flow and return header arrangement to support efficient operation.
  • A run and standby configuration was implemented, providing 100% redundancy and ensuring reliability in the event of unit failure.
  • All equipment was delivered, installed, and commissioned within a single day, meeting the project’s tight timeframe.

 

Royal Sussex County Hospital - Chiller    Royal Sussex County Hospital - Chiller      Royal Sussex County Hospital - Chiller

Location

Outcome

Rapid Energy successfully delivered 1440kW of temporary cooling capacity, restoring stability to the hospital’s system.

The temporary chillers took full load off the existing failing units, allowing them to safely shut down. The system quickly stabilised at 7°C, a level the hospital had not achieved in years, significantly improving overall performance.

All works were completed with zero disruption to hospital operations, ensuring continuity of critical services throughout.

This project demonstrates Rapid Energy’s ability to deliver fast, engineered solutions in high-pressure, complex environments, where reliability, safety, and speed are essential.

Royal Sussex County Hospital - Chiller

Get in touch

  • This field is for validation purposes and should be left unchanged.
  • Drop files here or
    Max. file size: 50 MB.
    • I would like Rapid Energy to contact me as below. I acknowledge that I may withdraw my consent or unsubscribe at any time and that you will not pass my details to anyone. By clicking the Ok button I agree to the privacy policy