Local authority leisure centres play a vital role in the community, offering recreational services such as fitness facilities, swimming pools, and sports activities. Many of these centres are now undergoing upgrades to reduce carbon emissions and improve sustainability.
One such centre was Towcester Centre for Leisure located in Northamptonshire. It offers a wide range of facilities including a 25m swimming pool, a leisure pool, a large gym, fitness studios, a sports hall, and a 3G outdoor pitch. It also features a café, accessible amenities, and a variety of programs for all ages, including group classes, children’s activities, and inclusive community initiatives.
Back in 2024, the centre started the process of decarbonising its infrastructure by removing outdated gas-fired heating systems and replacing them with eco-friendly Air Source Heat Pumps (ASHPs). However, the centre couldn’t afford to close its doors during the upgrade. They needed a reliable way to maintain heating and hot water while the transition was underway. That’s where Rapid Energy stepped in to assist – providing a seamless, temporary heating solution that allowed the leisure centre to remain operational.
Several challenges arose during the project, which required careful planning and creative solutions:
The installation process was carefully planned to avoid disruption while facilitating the decarbonisation upgrade. Key steps in the execution included:
With the strategic deployment of temporary heating equipment, Towcester Centre for Leisure was able to:
This project demonstrates the value of well-planned temporary heating solutions during major infrastructure upgrades. By partnering with us, Towcester Centre for Leisure was able to maintain essential services while moving forward with its decarbonisation efforts. The result was an environmentally friendly upgrade completed without compromising the comfort or safety of users.