Project Background

Rapid Energy received an emergency call from a facilities management (FM) client following a boiler failure at a secure facility in Lincolnshire, which had resulted in the loss of heating and hot water. With both services essential to the day-to-day operation of the facility, the client needed a temporary boiler hire solution that could be mobilised quickly and restore the site to normal operation with minimal downtime.

The FM client called Rapid Energy late on a Friday afternoon, speed of response was critical, so the team immediately began working towards restoring the facility’s essential services.

300kW Slimline Condensing Gas Boiler

Equipment Supplied

  • 2 × 300kW slimeline condensing gas boiler
  • Temporary plate heat exchanger
  • Temporary circulation/pump equipment
  • Flexible flow and return hoses
  • Associated temporary pipework, valves and connections

Challenges

  • The emergency call was received at 3:30pm on a Friday, leaving a limited window to assess the requirements and mobilise resources ahead of the weekend.
  • The boiler failure had left the facility without both heating and hot water, preventing normal operation.
  • The correct temporary boiler equipment needed to be confirmed quickly through an on-site assessment.
  • The secure nature of the facility meant site access and installation logistics had to be carefully planned around existing site requirements.

Rapid Energy 300kW temporary boilers

Our Solution

Rapid Energy immediately began coordinating the engineers, transport and equipment required for the emergency boiler installation.

  • By 5:30pm on Friday, the site requirements had been reviewed and a quotation issued, allowing mobilisation to progress without delay.
  • A senior engineer was mobilised within four hours of the initial call and attended the facility that evening to carry out a detailed site survey.
  • The survey confirmed the equipment and installation requirements, allowing the team to proceed with 2 × 300kW slimline condensing gas boilers.
  • At the same time, our depot team worked into the evening preparing the temporary boilers and associated equipment for transportation the following morning.
  • Our engineers arrived on site at 9:00am on Saturday, with the boilers arriving approximately 30 minutes later.
  • The two boilers provided 600kW of combined temporary heating capacity and were installed alongside the necessary temporary connections and associated equipment.
  • By 2:00pm on Saturday, the system had been commissioned and the facility’s heating and hot water were restored.

Throughout the response, the Rapid Energy team kept the client and their contractor updated as each stage progressed, helping the installation run smoothly from the initial call through to commissioning.

Rapid Energy 300kW temporary boilers

Location

Outcome

Heating and hot water were successfully restored within 24 hours of the initial emergency call, allowing the secure facility to return to operation and minimising disruption for the client.

By preparing equipment at the depot while the evening site survey was taking place, Rapid Energy was able to progress multiple stages simultaneously and reduce the overall time required to restore the site’s essential services.

The client was particularly pleased with the support provided throughout the emergency response and the speed at which the team mobilised to get the facility operational again.

Contact Rapid Energy to discuss your temporary boiler hire requirements.

Customer Quote

“From late Friday afternoon through to the completion of the works on Saturday, Emma [Key Account Manager at Rapid Energy] maintained constant communication, providing regular updates and making herself readily available to answer calls and respond to any queries. Her proactive approach, responsiveness, and commitment to keeping all parties informed made what was a highly pressured situation run as smoothly as possible.

Emma’s support was invaluable and greatly appreciated by both myself and our client. Her coordination, alongside the efforts of the attending engineers, played a significant role in achieving a successful outcome.”

Facilities Management Client

Get in touch

  • This field is for validation purposes and should be left unchanged.
  • Drop files here or
    Max. file size: 50 MB.
    • I would like Rapid Energy to contact me as below. I acknowledge that I may withdraw my consent or unsubscribe at any time and that you will not pass my details to anyone. By clicking the Ok button I agree to the privacy policy